Decision Maker: Greater Manchester Combined Authority
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Decision:
- That the current
2023/24 forecast of £579.1m compared to the 2023/24 previous
forecast of £623.6m be noted and that changes to the capital
programme, as set out in the report and Appendix A, be
approved.
- That the capital
programme budget for 2024/25 of £685.2m and the forward plan
for future years, as set out in the report and Appendix A, be
approved.
- That the addition to,
and the subsequent drawdown from, the 2023/24 capital programme of
£4.4m for local highways maintenance activities, as outlined
in section 3.9.4 of this report, be approved.
- That the inclusion of
Trailblazer funding, as outlined in section 4.14 of the report, be
approved.
Publication date: 12/02/2024
Date of decision: 09/02/2024
Decided at meeting: 09/02/2024 - Greater Manchester Combined Authority
Effective from: 20/02/2024
Accompanying Documents: