Decision status: For Determination
Is Key decision?: Yes
Is subject to call in?: No
· that it be noted that the Full Business Case health check has recently been undertaken
· that it be noted that GM Chief Executives have (in line with agreed governance) agreed the allocation of Growth Deal programme contingency allowance to the scheme
· that the remaining contribution of £8.845 million from the Mayors Challenge Fund (MCF) to provide the full, overall, contribution to the scheme from the MCF of £11.263 million be approved
· that Final Full Approval to the scheme be granted to enable a contract for the main construction works to be awarded and for the scheme to progress.
Publication date: 21/12/2021
Date of decision: 17/12/2021
Decided at meeting: 17/12/2021 - Greater Manchester Combined Authority
Accompanying Documents: