Decision status: For Determination
Is Key decision?: Yes
Is subject to call in?: No
2. That the conditions and details for this submission as set out in section 1 of the report be noted.
3. That the GMCA financial contribution of £12.5m be provisionally approved, that will be financed by prudential borrowings, noting that the borrowings will be repaid to GMCA over the lifetime of the assets through a subsidy control clawback mechanism; and that it be further noted that in the event that the submission is successful, final approval would be sought once costs have been confirmed.
4. That it be noted that any assets created through this fund would be available for the future franchised GM bus network.
Publication date: 01/02/2022
Date of decision: 28/01/2022
Decided at meeting: 28/01/2022 - Greater Manchester Combined Authority
Accompanying Documents: