Decision:
- That the current
position in relation to the transport infrastructure pipeline be
noted.
- That the proposals
for the reprioritisation of CRSTS1 capital funding, as detailed
within Section 3 of the report, be approved.
- That the proposals
for the allocation of CRSTS1 revenue funding for 2025/26, as set
out in section 3 of the report, be approved.
- That the proposals
for additional Highways Maintenance funding, as set out in Section
4 of the report, be approved.
- That the proposals to
review arrangements for Highways Network Management, as set out in
Section 4 of the report, be noted.
- That the proposed
list of prioritised schemes to support the delivery of the
Integrated Pipeline, detailed in Section 5 and Appendix 1 of the
report, be approved.
- That the proposed
list of prioritised schemes for the receipt of funding to support
the delivery of the Bee Network, detailed in Section 6 and Appendix
2 of the report, be approved.
- That the outline
proposals for the funding to support the delivery of Active Travel
improvements, set out in Section 7 of the report, be noted and that
officers be requested to submit detailed proposals on the
prioritisation of these allocations to the next meeting of the
GMCA.
- That the proposals in
relation to the Potential Capital to Revenue ‘switch‘,
as set out in Section 8 of the report, be noted.
- That the allocation
of the of the additional CRSTS1 revenue funding, set out in Section
9 of the report, be approved.
- That the next steps,
as set out in Section 10 of the report, be approved.
- That it be noted that a drawdown of capital funding of 15% of the budgeted cost for
each scheme, detailed in Appendix One and Two of the report, has
been sought from the Bee Network Committee, subject to the approval
of Recommendations 5 and 6 to facilitate the immediate progression
of these schemes.
- That it be noted that a drawdown of capital funding totalling £10.2m for Local
Authority Highways Maintenance, which represents the portion of the
overall £25m allocation, detailed in Section 4 of this
report, derived from headroom in the CRSTS1 pipeline, has been
sought from the Bee Network Committee, subject to the approval of
Recommendation 4.
Publication date: 01/07/2025
Date of decision: 27/06/2025
Decided at meeting: 27/06/2025 - Greater Manchester Combined Authority
Effective from: 09/07/2025
Accompanying Documents: