Decision details

The Mayor's Cycling and Walking Challenge Fund (MCF)

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Decision:

1.      That the agreed MCF delivery priorities across GM and the prioritised first phase for the programme, as set out in Appendix 1 of the report be noted.

 

2.      That the release of up to £1.3 million of development cost funding for the 4 MCF schemes set out in section 2 of the report be approved.

 

Publication date: 02/02/2021

Date of decision: 29/01/2021

Decided at meeting: 29/01/2021 - Greater Manchester Combined Authority

Effective from: 09/02/2021

Accompanying Documents: