1. That the release of up to £0.573 million MCF funding for the Manchester Beswick Phase 2 scheme be approved, in order to secure full approval and enable the signing of the necessary legal agreements, as set out in section 2 of the report.
2. That the release of up to £11.88 million MCF funding for the Greater Manchester Bike Hire scheme (Phase 1) be approved, in order to secure full approval and enable the signing of the necessary legal contracts for the scheme, as set out in section 2 of the report (and approve TfGM entering into such contracts).
3. That it be noted that the ‘Streets for All’ report will be submitted to the GMCA in July 2021.
Publication date: 29/06/2021
Date of decision: 25/06/2021