- That the progress made in relation
to the Growth Deal Transport schemes, as set out in Section 3 and 4
of the report, be noted.
- That the progress made in relation
to the Non-Transport Skills Capital and Economic Development and
Regeneration (ED &R) programmes, as set out in Section 6 of the
report, be noted.
- In relation to the Stockport Mixed
Use scheme:
·
that it be noted that the Full Business Case health check has
recently been undertaken
·
that it be noted that GM Chief Executives have (in line with agreed
governance) agreed the allocation of Growth Deal programme
contingency allowance to the scheme
·
that the remaining contribution of
£8.845 million from the Mayors Challenge Fund (MCF)
to provide the full, overall, contribution to the
scheme from the MCF of £11.263 million be approved
·
that Final Full Approval to the scheme be granted to enable a
contract for the main construction works to be
awarded and for the scheme to progress.
- That the expenditure approval of
Growth Deal funding for the remaining two packages of the Oldham
Town Centre Regeneration works, as set out in Section 5 of the
report, be agreed, subject to confirmation of the funding and
approval by the Chief Executive Officer, GMCA & TfGM.